Offshore Engineering of Guangdong Yangjiang Nuclear Power Plant
The project is located in Yangjiang, Guangdong Province, with 6 generator units of a total installed capacity of 6,000 MW. The marine design work includes a 980 meters long protection dike for the east platform, the 930 meters long south breakwater, the 250 meters long west breakwater, the 307 meters long west protection dike, the 609 meters long revetment for the pre-fabrication area, the 410 meters long breakwater for the intake, the 560 meters long revetment for the wave dissipation tank, the 328 meters long revetment for expert village, a bridge across the nullah and a 5,000DWT terminal for large equipment unloading.